If your estate or community has purchased, or intends to purchase, electricity infrastructure to facilitate or improve electricity supply to your area, Nigerian electricity law recognises this as an investment in the electricity distribution network.
If your estate or community has purchased, or intends to purchase, electricity infrastructure to facilitate or improve electricity supply to your area, Nigerian electricity law recognises this as an investment in the electricity distribution network. This means that, subject to the applicable regulatory requirements and the terms of the arrangement with the Distribution Company (DisCo), the residents’ association may be entitled to recover the cost of the investment, including its capital contribution. We highlight some key considerations that residential estates and other private investors may consider before purchasing transformers and other electricity distribution infrastructure. The considerations are necessarily impacted by the extant electricity deregulation legislation.
1. Residents are not ordinarily responsible for financing a DisCo’s network
The responsibility for developing, maintaining and expanding an electricity distribution network rests primarily with the DisCo operating that network. Under the NERC Investment in Electricity Networks Regulation 2015, distribution licensees are responsible for forecasting future demand, planning network expansion and identifying and correcting problems affecting the quality and reliability of electricity supply.
Accordingly, residents should not ordinarily be required to purchase transformers, electricity poles, cables or other network assets as a condition for connecting their estate or community to electricity supply. Equally, residents should not be required to contribute towards the repair or replacement of the DisCo’s existing assets, except where the damage is attributable to their wilful conduct.
This does not, however, prevent residents from voluntarily financing additional infrastructure to improve electricity supply, extend the distribution network or facilitate a new connection. The important distinction is between being compelled to finance the DisCo’s obligations and voluntarily making an investment under an arrangement that protects the financial interests of the residents.
2. Residents’ associations can invest in electricity distribution networks
The Nigerian Electricity Regulatory Commission (NERC) issued the Investment in Electricity Networks Regulation 2015 to establish a framework for investment in electricity infrastructure by persons and organisations other than licensed electricity operators.
The Regulation recognises that individuals, corporate bodies, organisations and institutions may invest in electricity networks owned, operated and maintained by licensed operators.
This is particularly relevant to residents’ associations, community development associations and property developers who may wish to finance the installation of transformers, distribution lines, electricity poles and other infrastructure necessary to improve electricity supply.
Under Regulation 7, a non-licensee wishing to invest in a licensed distribution network is required to enter into a Project Agreement with the relevant licensee. The agreement must address the investor’s capital contribution, procurement, construction, commissioning, formal handover, connection to the network, payment or amortisation schedule and dispute resolution.
The important point is that the Regulation contemplates an investment arrangement, not simply a donation of infrastructure to the DisCo. Indeed, Regulation 15(v) expressly provides for regulatory approval of agreements covering the reimbursement of investments made by third parties.
In other words, there is a regulatory framework for residents’ associations and other third-party investors to recover the cost of infrastructure they finance for a DisCo’s network.
3. Residents’ associations should not purchase electricity infrastructure without a Project Agreement
A common practice is for residents of an estate or community to contribute money towards the purchase of a transformer. The residents’ association raises the money, purchases the equipment and presents it to the DisCo for installation and energisation.
The problem is that these arrangements are often concluded informally. There may be receipts for the transformer, correspondence with DisCo officials and evidence of the residents’ expenditure, but no formal agreement establishing the financial and legal consequences of the investment. This creates significant problems when the residents’ association subsequently seeks reimbursement. Thus, residents’ associations should not rely on verbal assurances from DisCo officials that their investments will be reimbursed. The terms should be properly documented before funds are committed.
Regulation 7(iii) of the 2015 Regulation requires a Project Agreement between the investor and the relevant licensee. Among other things, the agreement should address:
Project scope: The infrastructure to be provided and the purpose of the investment.
Capital contribution: The amount being invested by the residents’ association and how it relates to the applicable tariff framework.
Procurement: Who will procure the equipment, the applicable specifications and the procurement process.
Construction and commissioning: Who is responsible for installation, testing and commissioning.
Handover: The terms upon which the completed infrastructure will be handed over and connected to the DisCo’s network.
Reimbursement: The payment or amortisation schedule through which the investor will recover the investment.
Dispute resolution: The procedure for resolving disagreements between the parties.
The agreement must be submitted by the DisCo to the applicable regulator for approval. Under the 2015 Regulation, the regulator is required to communicate its decision within 30 days of receiving the application and the necessary supporting documents. If approval is not communicated within that period, Regulation 7(vii) provides that the agreement may be executed by the parties.
Where residents have already financed infrastructure without a formal Project Agreement, the absence of that agreement does not, by itself, answer the question of whether the residents’ association has any enforceable rights or potential claim in respect of its investment. The circumstances in which the investment was made, any representations by the DisCo, correspondence between the parties and available payment and procurement records may all be relevant in assessing the association’s legal position and possible avenues for recovery. The position should therefore be assessed on the available facts rather than assumed to be lost simply because a formal agreement was not executed.
Balogun Harold advises electricity licensees, residents’ associations, community development associations, estate developers and businesses on electricity infrastructure investments and regulatory compliance.
This publication is provided for general information only and does not constitute legal advice. Readers should seek specific advice before acting on any matter discussed.